Mira Compressor Station Project

 

The Mira Compressor Station Project involves construction of the final compressor station originally approved as part of the Gulf Crossing Project.  Construction of the Project commenced in August 2009.  On March 12, 2010, the Mira Compressor Station Project was placed in service - increasing Gulf Crossing’s peak-day transmission capacity to approximately 1.7 Bcf per day.