Mira Compressor Station Project

 

TIMELINE

 

April 30, 2008

FERC issued Certificate authorizing construction of the Gulf Crossing Project ("April 30 Certificate")

 

December 5, 2008

Filed Application to amend April 30 Certificate to upgrade certificated units at the Mira Compressor Station

 

June 26, 2009

FERC issued "Order Amending Certificate" which amended the April 30 Certificate and authorized construction of the upgraded Mira Compressor Station

 

August 2009

Start of construction for Mira Compressor Station

 

March 12, 2010

Mira Compressor Station placed in service